Installing the doors/windows in the PMR gîte (day 1)
After 10 weeks on order, the doors and windows for the PMR gîte and events barn are ready to be installed and the guys started today on the gîte.
Although wooden windows would have been beautiful and more in keeping with the history of the chateau, a lot of them have already been replaced with white PVC so it made sense to keep them consistent, plus wood is over 3 times the cost of PVC and needs maintenance.
Lounge window |
Small kitchen window |
Kitchen door which will have a ramp for wheelchair access |
Ground floor PMR bedroom, leading onto the terrace |
Small window next to staircase |